Design Review Submittal Procedures
PSUs and their Design Teams are responsible for making timely and complete project review submittals and including adequate review periods when developing project schedules. School Planning typically issues design review comments within 30 days of each design phase submittal. Upon completion of the design review process, a Certificate of Review will be issued for the project.
NOTE! Schematic Design (SD) review meetings are available for all projects. We offer two meeting options – virtual or in-person. When a new submittal is received for large or complex projects, an assigned reviewer will contact the design team to schedule an SD review meeting time. This effort is intended to ensure that any critical project issues are identified early to allow timely resolution without disruption of ongoing design work.
Send all correspondence and design review submittals electronically – via email – to Teri Williams: teri.williams@dpi.nc.gov
Provide 3 PDF files with each submittal:
- DPI Project Transmittal Form
- Drawings
- Specifications
Electronic Design Review Submittal
PDF format - DPI Transmittal, Drawings, Specifications: Electronic Submittal
School Planning professionals conduct design reviews for new schools, additions, and renovations. Design reviews ensure that school facilities accommodate modern educational program requirements.
Design reviews encompass code compliance, life safety, longevity, durability, economy, and efficiency of building construction systems. Comments address local program flexibility while providing accountability with regard to the North Carolina Public Schools Facilities Guidelines.
Design review conferences are available at each design phase, offering design teams and school administrators the opportunity to meet with the School Planning staff of architects, engineers, and programmatic specialists.
Electronic Submittal of Design Reviews is now Required
Please send all correspondence and design review submittals electronically – via email or download link – to Teri Williams at: teri.williams@dpi.nc.gov
Submittal Materials
SD Phase - 100% complete
- Project Submittal Form (PDF format)
- Drawings (single PDF file)
- Specifications or Design Narrative (single PDF file)
DD Phase - 100% complete
- Project Submittal Form (PDF format)
- Written Responses to SD Review Comments (PDF format)
- Drawings (single PDF file)
- Specifications (single PDF file)
CD Phase - 95% complete (minimum)
- Project Submittal Form (PDF format)
- Written Responses to DD Review Comments (PDF format)
- Drawings (single PDF file)
- Specifications (single PDF file)
Architecture / Media Center / Site Design
- Fred Jernigan, AIA | 984-236-2462
- Leanne Lawrence, AIA | 984-236-2243
- Tom Hughes, AIA | 984-236-2929
Structural Engineering
- Dennis Hilton, PE | 984-236-2922
Mechanical Engineering
- Frankie Sykes, PE | 984-236-2924
Electrical Engineering
- Jon Jones, PE | 984-236-2918